Day 1, Monday 22 July, 2013

We started by transporting from my house to the Saxion all pre-produced panels and other materials.

 

We organized tables, cleaned them and covered them with protection sleeves and started to layout the basic configuration.

The scaffolding is impressive!

Paul Hildebrandt and I were very happy that Jim Hausman arrived early after a long drive from Paris!
There was some confusion about the basis...
We decided to start upside-down since this guarantees the best the planarity and integrity of the basis.

 

At the end of the afternoon, we really made progress, fully according to schedule.

 

 

A time-lapsed video of day 1

 

An edited video recording of day 1.